考试网 >> 职业资格 >> 项目管理师 >> 项目管理指导 >> 考前模拟试题(二)及参考答案

考前模拟试题(二)及参考答案

发布时间:2006-06-29 05:35     点击:
分页:上一页  1 2 3 [4] 

  C. Paying for work accomplished to date.

  D. Negotiating a change to the payment conditions in the contract.

  18. A precise description of a physical item, procedure, or service for implementation of an item or service is called :

  A. Work package.

  B. Baseline.

  C. Product description.

  D. Work breakdown structure (WBS) element.

  19. A project should be terminated for all of the following reasons except:

  A. Lack of team synergy.

  B. The project no longer meets the company's objectives.

  C. The resources are not available to complete project activities.

  D. Project funding has been significantly reduced.

  20. One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and:

  A. Divide it by the schedule performance index.

  B. Multiply it by the schedule performance index.

  C. Multiply it by the cost performance.

  D. Divide it by the cost performance index.

  参考答案:

  1.B 2.B 3.C 4.D 5.D 6.C 7.C 8.A 9.D 10.D 11.D 12.D 13.B 14.B 15.C 16.D 17.B 18.C 19.A 20.D
分页:上一页  1 2 3 [4] 
版权申明:未经书面授权请勿转载本站信息!!作品版权归所属媒体与作者所有!!
发表评论: 匿名发表 用户名: 查看评论
您将承担一切因您的行为、言论而直接或间接导致的民事或刑事法律责任
留言板管理人员有权保留或删除其管辖留言中的任意内容
本站提醒:不要进行人身攻击。谢谢配合。
在本站搜索相关信息
2003-2005 Ksw123.com All Rights Reserved. - TOP
Copyright © 2006 Ksw123.com. All rights reserved.中国考题网 版权所有