C. Paying for work accomplished to date.
D. Negotiating a change to the payment conditions in the contract.
18. A precise description of a physical item, procedure, or service for implementation of an item or service is called :
A. Work package.
B. Baseline.
C. Product description.
D. Work breakdown structure (WBS) element.
19. A project should be terminated for all of the following reasons except:
A. Lack of team synergy.
B. The project no longer meets the company's objectives.
C. The resources are not available to complete project activities.
D. Project funding has been significantly reduced.
20. One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and:
A. Divide it by the schedule performance index.
B. Multiply it by the schedule performance index.
C. Multiply it by the cost performance.
D. Divide it by the cost performance index.
参考答案:
1.B 2.B 3.C 4.D 5.D 6.C 7.C 8.A 9.D 10.D 11.D 12.D 13.B 14.B 15.C 16.D 17.B 18.C 19.A 20.D