Qustions 1:

1. The process of determining who needs what information, when they need it, and how it will be given to them is:

A. Information distribution

B. Communications requirements

C. Communications planning

D. Communications management

Qustions 3:

Which of the following is not a technology factor that may affect the project communications plan:

A. Immediacy of the need for the information

B. Length of the project

C. Expected project staffing

D. Logistics of how many individuals will be involved with

the project and at what locations

Qustions 5:

Which of the following is not a type of performance reporting:

A. Status reporting

B. Progress reporting

C. Forecasting

D. Benchmark reporting

Qustions 2:

Communication planning is most ti~tly linked with what process:

A. Cost estimating

B. Organizational planning

C. Cost budgeting

D. Performance reporting

Qustions 4:

Where is the bulk of the project budget spent?

A. Scope management

B. Production

C. Labor and materials

D. Project plan execution

Qustions 6:

Which tool and technique integrates scope, cost and schedule in measuring project performence?

A. Variance analysis

B. Earned value

C. Trend analysis

D. Performance report

Qustions 1:
分页:[1] 2  下一页
版权申明:未经书面授权请勿转载本站信息!!作品版权归所属媒体与作者所有!!
发表评论: 匿名发表 用户名: 查看评论
您将承担一切因您的行为、言论而直接或间接导致的民事或刑事法律责任
留言板管理人员有权保留或删除其管辖留言中的任意内容
本站提醒:不要进行人身攻击。谢谢配合。
在本站搜索相关信息
2003-2005 Ksw123.com All Rights Reserved. - TOP
Copyright © 2006 Ksw123.com. All rights reserved.中国考题网 版权所有