PMP模拟题精选12

发布时间:2006-06-29 01:28     点击:
分页:上一页  1 [2] 

d. Project closure and lessons learned 

Qustions 4:

During the schedule development process the Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:

a. Critical Path Method, GERT, Resource Requirements 

b. Resource Leveling Heuristics, Mathematical Analysis, Calendars 

c. Duration compression, Resource Leveling Heuristics, PERT 

d. GERT, PERT, Leads and Lags 

Qustions 6:

The “To Complete Performance Index” (TCPI) is calculated by: 

a.

Subtracting the actual costs to date from the estimate at completion 

b.

Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date 

c.

Multiplying the estimate at completion by the cumulative cost performance index 

d.

Adding the estimate at completion to the actual costs to date and multiplying by the cumulative cost performance index 
分页:上一页  1 [2] 
版权申明:未经书面授权请勿转载本站信息!!作品版权归所属媒体与作者所有!!
发表评论: 匿名发表 用户名: 查看评论
您将承担一切因您的行为、言论而直接或间接导致的民事或刑事法律责任
留言板管理人员有权保留或删除其管辖留言中的任意内容
本站提醒:不要进行人身攻击。谢谢配合。
在本站搜索相关信息
2003-2005 Ksw123.com All Rights Reserved. - TOP
Copyright © 2006 Ksw123.com. All rights reserved.中国考题网 版权所有