d. Project closure and lessons learned
Qustions 4:
During the schedule development process the Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:
a. Critical Path Method, GERT, Resource Requirements
b. Resource Leveling Heuristics, Mathematical Analysis, Calendars
c. Duration compression, Resource Leveling Heuristics, PERT
d. GERT, PERT, Leads and Lags
Qustions 6:
The “To Complete Performance Index” (TCPI) is calculated by:
a.
Subtracting the actual costs to date from the estimate at completion
b.
Dividing the budgeted cost of the remaining work by the difference between the estimate at completion and actual costs to date
c.
Multiplying the estimate at completion by the cumulative cost performance index
d.
Adding the estimate at completion to the actual costs to date and multiplying by the cumulative cost performance index