c. Alerts the project team to issues that may cause problems in the future
d. Is expected to change throughout the project
Qustions 2:
Written changes orders should be required on --
a. All projects, large and small
b. Large projects
c. Projects with a formal configuration management system in place
d. Projects for which the cost of a change control system can be justified
Qustions 4:
The principal sources of project failure are-
a. Lack of a projectized or strong matrix structure, poor scope definition, and lack of a project plan
b. Lack of commitment or support by top management, disharmony on the project team, and lack of leadership by the project manager
c. Poorly identified customer needs, a geographically dispersed project team, and little communication with the customer until the project is delivered
d. Organizational factors, poorly identified customer needs, inadequately specified project requirements, and poor planning and control
Qustions 6:
Interface management is --