Qustions 1:
A change control system should include all the following except-
a.
Procedures for automatic approval of defined categories of change
b. Paperwork, tracking systems, and approval levels necessary for authorizing changes
c. A description of the powers and responsibilities of the change control board
d. Procedures for conducting a midproject control system review
Qustions 3:
Two fundamental objectives of project control are to--
a.
Alter activities to achieve results and manage organizational assets
b. Eliminate unexpected technical problems and identify technical difficulties that require more resources
c. Ensure that resources are available when needed and avoid increases in the scope of work
d. Have the required material, personnel, and equipment available when needed and ensure that budgeting is adequate
Qustions 5:
The project plan is important in change control because it--
a.
Provides the baseline against which changes are managed
b. Provides the information on project performance