Qustions 1:
A project is an ideal environment in which to use the technique of management by objectives because--
a.
Project management involves setting organizational objectives
b. Projects generally are handled through a matrix management environment
c. Project managers’ responsibilities are defined in terms of corporate objectives
d. All projects should be strongly oriented toward goals and objectives
Qustions 3:
All the following are examples of benefit measurement methods of project selection except--
a.
Benefit-cost ration
b. Payback period
c. Peer review
d. Multiobjective programming
Qustions 5:
Which of the following is a tool or technique used for project initiation--
a.
Alternatives identification
b. Configuration management
c. Decision models
d. Decomposition
Qustions 2:
Each project phase is marked by completion of one or more deliverables. The deliverable for the concept phase of a project is the--
a. Project plan
b. Statement of work