Qustions 1: 

A project is an ideal environment in which to use the technique of management by objectives because-- 

a.

Project management involves setting organizational objectives 

b. Projects generally are handled through a matrix management environment 

c. Project managers’ responsibilities are defined in terms of corporate objectives 

d. All projects should be strongly oriented toward goals and objectives 

Qustions 3:

All the following are examples of benefit measurement methods of project selection except--

a. 

Benefit-cost ration 

b. Payback period 

c. Peer review 

d. Multiobjective programming 

Qustions 5:

Which of the following is a tool or technique used for project initiation--

a.

Alternatives identification 

b. Configuration management 

c. Decision models 

d. Decomposition 

Qustions 2: 

Each project phase is marked by completion of one or more deliverables. The deliverable for the concept phase of a project is the-- 

a. Project plan 

b. Statement of work 
分页:[1] 2  下一页
版权申明:未经书面授权请勿转载本站信息!!作品版权归所属媒体与作者所有!!
发表评论: 匿名发表 用户名: 查看评论
您将承担一切因您的行为、言论而直接或间接导致的民事或刑事法律责任
留言板管理人员有权保留或删除其管辖留言中的任意内容
本站提醒:不要进行人身攻击。谢谢配合。
在本站搜索相关信息
2003-2005 Ksw123.com All Rights Reserved. - TOP
Copyright © 2006 Ksw123.com. All rights reserved.中国考题网 版权所有