Qustions 1:
The change control system includes--
a.
Procedures to define how documents may be changed
b. Specific change requests expected on the project and plans to respond to each one
c. Performance reports that forecast project changes
d. A description of the functional and physical characteristics of an item or system
Qustions 3:
Typically, change control systems include automatic approval of certain types of changes. An example of such a change is one that is--
a.
Suggested by the project sponsor
b. The result of an emergency
c. Suggested by the customer
d. Made mandatory by a new regulation
Qustions 5:
Rolling wave planning provides information on the work to be done--
a.
Throughout all phases of the project
b. For successful completion of the current phases of the project
c. For successful completion of the current phase and subsequent phases of the project
d. In the next phase of the project