4、You are working on the cost budget for one project. Which of the following is true?
A. This process assigns cost estimates to project activities including risks and contingency plans.
B. The cost baseline will be used to measure variances and future project performance.
C. This process assigns cost estimates for expected future period operating costs.
D. The cost baseline is the expected cost for the project.
4、你正在为一个项目进行成本预算,以下哪项是正确的?
A. 这个过程分配成本预算给包括风险和应急计划在内的项目活动
B. 成本基线用于评估偏差和将来的项目绩效
C. 这个过程分配成本预算给将来的周期运行成本
D. 成本基线是项目成本的期望值
答案:B. 成本基线用于评估偏差和将来的项目绩效
分析:将来的周期运行成本被认为是运行成本,不是项目成本的一部分
5、The project team should have a working knowledge of statistical process control to help conduct quality control activities. Of all the topics involved, which of the following is the most important for the team to understand?
A. Sampling and probability
B. Attribute sampling and variable sampling
C. Tolerances and control limits
D. Special causes and random causes
5、项目团队应该了解如何利用统计知识进行质量控制。在下面所有涉及的议题中,哪一个是项目团队最需要知道的?