1、During the first half of the project. five team members left for other projects without being replaced. two team members went on vacation without informing you. and other team members expressed uncertainty about the work they were to complete. In this situation. it is BEST if you create a _____for the second half of the project.

A. work breakdown structure

B. resource histogram

C. staffing management plan

D. responsibility matrix

1、在项目的前半段,有5个项目组成员离开到其它的项目去,而没有资源来替代。2个项目组成员在没有通知你的情况下去休假。其它的项目组成员对是否能够完成自己的工作表示怀疑。在这种情况下,你为项目后半段创建______是最合适的?

A. WBS。

B. 资源柱状图。

C. 人员配备管理计划。

D. 责任矩阵。

答案:C. 人员配备管理计划。

分析:人员配备管理计划描述了资源何时获取和如何离开。

2、A project control system:

A. monitors and controls the project’s schedules, costs, scope, budgets, etc.

B. is a mechanism which reacts to the current project status in order to ensure accomplishment of project objectives

C. is only needed on large "mega" projects 

D. is a system for controlling and executing project documentation in a uniform and timely manner
分页:[1] 2 3 4 5 6  下一页
版权申明:未经书面授权请勿转载本站信息!!作品版权归所属媒体与作者所有!!
发表评论: 匿名发表 用户名: 查看评论
您将承担一切因您的行为、言论而直接或间接导致的民事或刑事法律责任
留言板管理人员有权保留或删除其管辖留言中的任意内容
本站提醒:不要进行人身攻击。谢谢配合。
在本站搜索相关信息
2003-2005 Ksw123.com All Rights Reserved. - TOP
Copyright © 2006 Ksw123.com. All rights reserved.中国考题网 版权所有